Feb 19 (Reuters) - Constellation Energy Corp CEG.O:
SAYS AHEAD OF SCHEDULE ON CRANE CLEAN ENERGY CENTER LAUNCH, FIVE MONTHS AFTER ITS ANNOUNCEMENT AND LANDMARK POWER PURCHASE AGREEMENT WITH MICROSOFT TO RESTART THREE MILE ISLAND UNIT 1
SAYS HAS FILED AN INTERCONNECTION REQUEST WITH PJM TO ALLOW CRANE TO ADD ITS 835 MEGAWATTS OF EMISSIONS-FREE POWER TO THE GRID
SAYS IT PLANS TO HIRE MORE THAN 600 EMPLOYEES PRIOR TO THE RESTART
SAYS ONE OF THE LARGEST NEW EQUIPMENT PURCHASES REQUIRED FOR THE RESTART IS FOR CONSTRUCTION OF THREE NEW MAIN POWER TRANSFORMERS
SAYS CONTRACT HAS BEEN AWARDED AND AN ADDITIONAL $35 MILLION INVESTMENT WILL ENSURE THE MASSIVE TRANSFORMERS REACH THE STATION SAFELY IN 2026
Further company coverage: CEG.O