Shares of Cheniere Energy LNG.N rise 1.5% to $213.69
Company produces first liquefied natural gas from the first train (Train 1) of new Corpus Christi Stage 3 Liquefaction project (CCL Stage 3), in Texas
Says new plant consists of seven midscale trains, with an expected total production capacity of over 10 million tonnes per annum
Adds that as of Nov. 30, overall project completion for CCL Stage 3 was 75.9%
Cheniere expects substantial completion of Train 1 to be achieved at the end of the first quarter of 2025
Including session's moves, stock up 24.97% YTD
(Reporting by Pooja Menon in Bengaluru)