Aug 22 (Reuters) - The following table lists existing and proposed North American liquefied natural gas (LNG) export plants with future dates from energy companies or analysts' estimates.
Plant capacities in million tonnes per annum (MTPA) of LNG and billions of cubic feet per day (BCFD) of natural gas:
In Service | ||||||
Project | State/Province | Company | Final Investment Decision (FID) | First LNG delivery | MTPA of LNG | BCFD of gas |
Sabine Pass 1-2 | LA | Cheniere | Jul 2012 | Feb-Jul 2016 | 11.5 | 1.51 |
Sabine Pass 3-4 | LA | Cheniere | May 2013 | Jan-Jul 2017 | 11.5 | 1.51 |
Cove Point | MD | Berkshire Hathaway Energy | Oct 2014 | Mar 2018 | 5.8 | 0.76 |
Sabine Pass 5 | LA | Cheniere | Jun 2015 | Nov 2018 | 5.8 | 0.76 |
Corpus Christi 1-2 | TX | Cheniere | May 2015 | Dec 2018-Jun 2019 | 12.2 | 1.60 |
Cameron 1-3 | LA | Sempra | Aug 2014 | May 2019-May 2020 | 15.0 | 1.97 |
Freeport 1-3 (electric) | TX | Freeport LNG | Nov 2014 | Aug 2019-Apr 2020 | 16.3 | 2.14 |
Elba Island 1-10 | GA | Kinder Morgan/Blackstone | Nov 2016 | Oct 2019-Aug 2020 | 2.7 | 0.36 |
Corpus Christi 3 | TX | Cheniere | May 2018 | Dec 2020 | 6.1 | 0.80 |
Sabine Pass 6 | LA | Cheniere | Jun 2019 | Nov 2021 | 5.8 | 0.76 |
Calcasieu Pass 1-18 | LA | Venture Global LNG | Aug 2019 | Mar 2022 | 12.0 | 1.58 |
Fast LNG 1 - Altamira offshore | Mexico | New Fortress/CFE | Oct 2022 | Aug 2024 | 1.4 | |
Plaquemines Parish 1-36 | LA | Venture Global LNG | 24-train phase 1 - May 2022; 12-train phase 2 - Mar 2023 | Dec 2024 | 24.0 | 3.16 |
Corpus Christi Midscale 1-7 | TX | Cheniere | Jun 2022 | Feb 2024 | 11.5 | 1.51 |
LNG Canada 1 | BC | Shell | Oct 2018 | Jun 2025 | 7.0 | |
Under Construction | ||||||
Project | State/Province | Company | Final Investment Decision (FID) | First LNG delivery | MTPA of LNG | BCFD of gas |
Golden Pass 1 | TX | QatarEnergy, ExxonMobil | Feb 2019 | H2 2025 | 6.0 | 0.79 |
Costa Azul 1 | Mexico | Sempra | Nov 2020 | spring 2026 | 3.3 | |
LNG Canada 2 | BC | Shell | Oct 2018 | Mar 2026 | 7.0 | |
Golden Pass 2 | TX | QatarEnergy, ExxonMobil | Feb 2019 | H1 2026 | 6.0 | 0.79 |
Fast LNG 2 - Altamira onshore | Mexico | New Fortress/CFE | H1 2026 | 1.4 | ||
Golden Pass 3 | TX | QatarEnergy, ExxonMobil | Feb 2019 | H2 2026 | 6.0 | 0.79 |
Woodfibre LNG (electric) | BC | RGE Group's Pacific Energy Corp Ltd (70%)/Enbridge (30%) | Jun 2027 | 2.1 | ||
CP2 (Calcasieu Pass 2) Phase 1 | LA | Venture Global LNG | Jul 2025 | 2027 | 17.3 | 2.28 |
Port Arthur 1-2 | TX | Sempra | Mar 2023 | 2027-2028 | 13.5 | 1.78 |
Rio Grande LNG-Brownsville 1-3 | TX | NextDecade LNG | Jul 2023 | 2027-2028 | 16.2 | 2.13 |
Corpus Christi Midscale 8-9 | TX | Cheniere | Jun 2025 | 2028 | 3.3 | 0.43 |
Cedar LNG (electric) | BC | Haisla (50)/Pembina (50) | Jun 2024 | late 2028 | 3.3 | |
Woodside Louisiana LNG Phase 1 (former Driftwood) | LA | Woodside | Apr 2025 | 2029 | 16.6 | 2.18 |
Under Development | ||||||
Project | State/Province | Company | Final Investment Decision (FID) | Target Start Up | MTPA of LNG | BCFD of gas |
Lake Charles 1-3 | LA | Energy Transfer | Q4 2025 | ~2029 | 16.5 | 2.17 |
Commonwealth LNG Cameron Parish | LA | Commonwealth LNG | 2025 | Q1 2029 | 9.5 | 1.25 |
Rio Grande LNG-Brownsville 4 | TX | NextDecade LNG | 2025 | ~2029 | 5.4 | 0.71 |
Ksi Lisims LNG (electric) | BC | Western LNG, the Nisga'a Nation and Rockies LNG | 2025 | ~2030 | 12.0 | |
Port Arthur 3-4 | TX | Sempra | 2025 | 2029 | 13.5 | 1.78 |
Alaska LNG 1-3 | AK | Alaska Gasline Development | 2025 | 2031 | 20.0 | 2.63 |
CP2 (Calcasieu Pass 2) Phase 2 | LA | Venture Global LNG | mid 2026 | 6.7 | 0.88 | |
LNG Canada 3-4 | BC | Shell | 2026 | early 2030s | 13.0 | |
Sabine Pass 7-8 | LA | Cheniere | 2026 | 2029 | 13.0 | 1.71 |
CP3 (Calcasieu Pass 3) phase 1 | LA | Venture Global LNG | mid 2027 | 18.0 | 2.37 | |
CP3 (Calcasieu Pass 3) phase 2 | LA | Venture Global LNG | mid 2028 | 18.0 | 2.37 | |
Argent LNG at Port Fourchon LNG phase 1 | LA | Argent | 12.0 | 1.58 | ||
Gulfstream LNG | LA | Gulfstream LNG | 4.2 | 0.55 | ||
Magnolia LNG | LA | Glenfarne Group LLC | 8.8 | 1.16 | ||
Corpus Christi stage 4 | TX | Cheniere | 26.0 | 3.42 | ||
Plaquemines Parish Phase 3 | LA | Venture Global LNG | 10.7 | 1.40 | ||
Delfin Gulf of Mexico 1 | LA | Delfin Midstream | 3.0 | 0.39 | ||
Delfin Gulf of Mexico 2 | LA | Delfin Midstream | 3.0 | 0.39 | ||
Texas LNG Brownsville 1 & 2 | TX | Glenfarne Group LLC | 4.0 | 0.53 | ||
Freeport 4 | TX | Freeport LNG | 5.1 | 0.67 |