April 30 (Reuters) - INDIANA MICHIGAN POWER AEPIG.UL:
SAYS COOK NUCLEAR PLANT UNIT 1 COMPLETED SPRING 2025 REFUELING OUTAGE WHICH BEGAN MARCH 22, CONNECTING TO THE TRANSMISSION GRID AT 3:00 P.M., APRIL 30
SAYS UNIT 2 REMAINED SAFELY AT FULL POWER FOR THE DURATION OF THE 39-DAY UNIT 1 REFUELING OUTAGE
SAYS OUTAGE ALSO INCLUDED REPLACING REACTOR COOLANT PUMP MOTOR, INSPECTION AND MAINTENANCE ACTIVITIES ASSOCIATED WITH MAIN TURBINE AND MAIN GENERATOR, AND REPLACING IMPORTANT BATTERY SYSTEMS FOR SAFETY-RELATED AND NON-SAFETY-RELATED EQUIPMENT
SAYS AN UPGRADED OVERSPEED PROTECTION SYSTEM WAS INSTALLED FOR THE MAIN TURBINE AND MAIN FEED PUMP TURBINES
Related: [nL4N3Q316I]