Conferencia de resultados del 4T del ejercicio fiscal 2026 de Tamboran Resources (TBN): Primeras ventas de gas de Beetaloo
Tamboran Resources registró sus primeras ventas de gas desde la cuenca de Beetaloo, con volúmenes limitados a 25 terajulios diarios por la demanda estacional del Territorio del Norte. La empresa cerró el trimestre con un efectivo proforma de 240 millones de dólares y avances significativos en sus programas de estimulación y perforación. Las operaciones actuales priorizan dos pozos para establecer historiales de producción a largo plazo. La dirección prevé que las nominaciones se aproximen al nivel contractual de 40 terajulios diarios hacia finales del año, mientras evalúa el uso de arena local para reducir los costes de terminación en futuros pozos.
Conclusiones principales
- Tamboran Resources realizó sus primeras ventas de gas desde la cuenca de Beetaloo al mercado del Territorio del Norte. El gas llevaba fluyendo 20 días al momento de la llamada, con nominaciones limitadas a 25 terajulios por día debido a la demanda estacional.
- Tras la puesta en marcha, se espera que el Acuerdo de Venta de Gas entre en un periodo de suministro con cláusula «take-or-pay» que cubrirá 40 terajulios por día. Durante la puesta en marcha, Tamboran recibe el 75% del precio del gas debido a que el suministro es interrumpible.
- La campaña de estimulación SS-2 completó 178 etapas a lo largo de 30.000 pies laterales, incluyendo un récord en la cuenca de 12 etapas en un solo día. Diez etapas utilizaron arena roja de Beetaloo de origen local.
- La directiva estima que la arena local podría reducir los costes de terminación en 4 millones de dólares para un pozo con un tramo lateral de 10.000 pies, en comparación con la arena importada. Una adopción más amplia sigue dependiendo de los datos de producción a más largo plazo.
- Tamboran cerró el trimestre con 225 millones de dólares en efectivo y 31 millones de dólares en deuda no dispuesta. Incluyendo un ingreso condicional de 15 millones de dólares de Daly Waters Energy, el efectivo proforma fue de 240 millones de dólares.
- La instalación de compresión de Sturt Plateau se completó según lo previsto y aproximadamente 9 millones de dólares por debajo del presupuesto proyectado. La puesta en marcha y la optimización del equipo continúan en curso.
Datos financieros clave
| Métrica | Información del T4 del ejercicio fiscal 2026 | Comentarios |
|---|---|---|
| Ampliación de capital de abril | 186 millones de dólares netos de comisiones | Realizada mediante una oferta pública asegurada y ofertas de suscripción preferente para inversores institucionales y minoristas |
| Efectivo al cierre del trimestre | 225 millones de dólares | Disponible para respaldar la siguiente fase de desarrollo |
| Deuda no dispuesta | 31 millones de dólares | Destinada a financiar la instalación de compresión de Sturt Plateau |
| Efectivo proforma | 240 millones de dólares | Incluye 15 millones de dólares previstos de Daly Waters Energy, sujetos a condiciones previas |
| Rendimiento presupuestario de la instalación de compresión | Aproximadamente 9 millones de dólares por debajo de lo proyectado | La instalación se completó a tiempo |
| Precio del gas durante la puesta en marcha | 75% del precio del gas contratado | Refleja la naturaleza interrumpible del suministro durante la puesta en marcha |
| Ahorro potencial con arena local | 4 millones de dólares por pozo | Estimación para un tramo lateral de 10.000 pies frente a la arena importada |
Tamboran señaló que algunos ingresos y costes del proyecto piloto podrían capitalizarse bajo los US GAAP durante los próximos dos trimestres mientras continúa la puesta en marcha. Como resultado, los resultados de la cuenta de pérdidas y ganancias a corto plazo podrían no reflejar los movimientos de efectivo asociados.
Rendimiento operativo y del negocio
Las primeras ventas de gas marcaron la transición del proyecto piloto de la cuenca de Beetaloo al suministro comercial. Los volúmenes actuales están limitados por las nominaciones del Gobierno del Territorio del Norte y no por la capacidad declarada de los pozos. Tamboran está priorizando dos pozos para crear historiales continuos de producción y de tasa de declive, mientras que otros pozos se alternan según sea necesario para recuperar el agua de retorno y cumplir con las nominaciones.
El programa de estimulación de la plataforma SS-2 utilizó la flota de Liberty Energy y completó 178 etapas a lo largo de 30.000 pies laterales. El enfoque de fracturamiento en cremallera («zipper-frac») permitió operar hasta 20 horas y lograr un récord en la cuenca de 12 etapas en un solo día. Tamboran y Liberty también firmaron un memorando de entendimiento no vinculante relativo a la extensión de los servicios de estimulación y cable de adquisición («wireline»). Liberty tiene la intención de comenzar a introducir equipos de bombeo de menores emisiones a partir de 2027.
Diez etapas del pozo SS2-5H utilizaron arena roja de Beetaloo. La directiva informó que no hubo ningún impacto adverso en la presión de bombeo ni en la iniciación de las fracturas, mientras que los resultados de los trazadores indicaron un rendimiento coherente con las etapas vecinas («offset»). Tamboran planea realizar pruebas parciales adicionales en la plataforma SS-1 bantes de contemplar su uso en pozos completos.
En la plataforma SS-1, se completaron los dos primeros pozos de una campaña de perforación de tres pozos, mientras que el tercero sigue perforándose. El diseño mejorado de las brocas, las herramientas antivibración y las modificaciones en el equipo de perforación hicieron posibles velocidades récord de perforación a través de la formación Moroak y mayores tasas promedio de penetración en las secciones laterales. La directiva considera realista un tiempo de perforación de 25 días o menos, destacando que Tamboran ya ha perforado anteriormente un pozo en 24 días.
En el depocentro oriental, Santos inició los pozos de evaluación Jibera South 1H y Newcastle South 1H en EP 161. Tamboran posee una participación de trabajo del 25%. La lutita B sigue siendo el objetivo principal, habiéndose identificado potencial adicional de zonas productivas superpuestas («stacked-pay») en otros intervalos.
Perspectivas de la directiva
La directiva prevé que las nominaciones de gas del Territorio del Norte aumenten a medida que suban las temperaturas y la demanda eléctrica durante la estación lluviosa. Tamboran señaló que las nominaciones podrían aproximarse al nivel contractual de 40 terajulios por día para finales del año natural, aunque el momento exacto dependerá de la demanda de los clientes. Las restricciones estacionales podrían regresar al año siguiente y requerir la desconexión de algunos pozos adicionales.
Una vez completadas la puesta en marcha y las pruebas de producción, Tamboran prevé que el suministro pase al periodo con cláusula «take-or-pay» de 40 terajulios por día. El gas no retirado por el comprador se acumularía como saldo reservado para una eventual entrega futura.
La empresa prevé publicar sus primeras ventas trimestrales de gas e ingresos con los resultados del T1 del ejercicio fiscal 2027 en noviembre. Planea centrar sus campañas de los ejercicios fiscales 2027 y 2028 en la delimitación de recursos en ambos depocentros de Beetaloo, incluyendo al menos seis pozos de delimitación («step-out») durante los próximos 18 meses junto con Daly Waters Energy, INPEX y Santos.
El programa de capital más amplio dependerá en parte de la selección de un socio estratégico y del acuerdo sobre el programa de trabajo asociado. La directiva afirmó que las conversaciones avanzan, pero no facilitó un cronograma para la transacción.
Riesgos y áreas de interés
- Tamboran cuenta con menos de 90 días de historial de producción en cualquiera de sus pozos, lo que limita la visibilidad sobre las tasas de declive y recuperación a largo plazo.
- La arena roja de Beetaloo se ha comportado según lo esperado en las primeras pruebas de bombeo y trazadores, pero su durabilidad ante el estrés cambiante del yacimiento requiere un historial de producción más prolongado.
- Los volúmenes de ventas actuales dependen de las nominaciones del Gobierno del Territorio del Norte y están expuestos a los cambios de la demanda estacional hasta que comience el suministro con cláusula «take-or-pay».
- La ampliación de la instalación de compresión de Sturt Plateau depende de la confianza en que la infraestructura de gasoductos adyacente perteneciente a terceros pueda transportar el gas incremental a mercados adicionales.
- El momento y el alcance del gasto de capital futuro siguen vinculados a las negociaciones con socios estratégicos y a la alineación sobre las prioridades de desarrollo.
- Se prevé que los acuerdos vinculantes de venta de gas en la Costa Este requieran una definición más clara de los recursos y una mayor reducción de riesgos en el subsuelo.
Puntos destacados del turno de preguntas de los analistas
Los analistas se centraron en la eficiencia de perforación, los datos de declive de los pozos, la escalabilidad de la arena local, el gasto de capital y el desarrollo de gasoductos.
La directiva atribuyó la mejora del rendimiento de perforación al rediseño de las brocas, herramientas antivibración, planes direccionales revisados y un mejor control de la temperatura del equipo. La repetición, las cuadrillas estables y una mayor actividad en toda la cuenca se identificaron como los requisitos principales para avanzar hacia un desarrollo de esquisto de menor coste.
En cuanto a la producción, la directiva afirmó que los dos pozos priorizados estaban rindiendo en línea con las expectativas y mostraban datos de presión satisfactorios. La principal cuestión pendiente es cómo declinará la producción con el tiempo. Otros pozos podrían contribuir a medida que aumenten las nominaciones, pero solo se prevé dar prioridad a dos para mantener historiales de rendimiento sostenido a largo plazo.
Tamboran no planea utilizar arena local en la totalidad de un pozo hasta contar con suficiente evidencia de producción. La empresa evaluará si las etapas con arena roja mantienen su contribución relativa a medida que disminuye la presión del yacimiento. Si el rendimiento sigue siendo comparable, la directiva señaló que la arena local podría llegar a representar prácticamente todo el agente de sostén («proppant») utilizado en la cuenca.
En relación con la infraestructura de la Costa Este, la directiva indicó que APA está avanzando en los permisos y los trabajos de derecho de paso. Sin embargo, se prevé que los compromisos comerciales vinculantes se alcancen tras obtener datos de producción adicionales y resultados de evaluación que establezcan una base de recursos más clara.
Transcripción completa de la llamada de resultados
Transcripción completa de la conferencia de resultados
Comentarios de la dirección
Operator
Greetings, and welcome to the Tamboran Resources Fourth Quarter Fiscal Year 2026 Earnings Call. [Operator Instructions] As a reminder, this conference is being recorded. [Operator Instructions] It's now my pleasure to turn the call over to Todd Abbott, Chief Executive Officer. Todd, please go ahead.
Todd Abbott
Hello, everyone, and welcome to Tamboran Resources Financial Year 2026 Fourth Quarter Earnings Presentation. My name is Todd Abbott, and I'm the Chief Executive Officer of Tamboran Resources. I'm joined here today by Chief Financial Officer, Eric Dyer; and VP, Investor Relations and Corporate Development, Chris Morbey.
I'll start by reviewing delivery against the commitments we made 12-months ago, then cover production and commissioning as we build towards plateau rates and contracted supply. I will also discuss what our latest well results and operating improvements mean for our performance and cost as we continue to derisk our asset. I will then review our funding position and close with the next development milestones before we take your questions.
Moving to Slide 2, you can see our disclaimer, which relates to forward-looking statements within the presentation. I encourage you to review those at your convenience.
On Slide 3. The last few months have been a pivotal period for Tamboran and the Betaloo Basin as we have delivered on a key commitment and provided the next step in derisking the basin. We have delivered First Gas Sales from the Betaloo to the Northern Territory Gas market. Homes and businesses in Darwin are now being powered by a local onshore resource. These gas sales also bring royalties to the Northern Territory Government and native title holders alongside job opportunities for Territorians. Tamboran already employs a significant local workforce, which we expect to grow as activity increases over the coming years.
Moving to Slide 4. Gas has now been flowing into the market for 20 days. Volumes are currently limited by market demand with the Northern Territory Government nominating 25 terajoule per day as the territory comes out of its lower demand season. We expect demand and therefore, nominations to keep growing through the Northern Territory's peak demand period. We are currently in the commissioning period of the Gas Sales Agreement. Once the agreement moves into the supply period, take-or-pay provisions will apply to the 40-terajoule per day contract quantity, and we will be getting revenue based on that 40-terajoules per day. Any gas the offtaker does not take will be banked for future potential delivery. This gives us downside protection in the event of lower nominations during the contracted period.
Regarding our flowback strategy, we will prioritize 2 wells to ensure that we're generating long-term production and well performance data to further derisk the basin. The remaining wells will be managed as needed to recover flowback water and to close any gap to the allowable nominations. In achieving this first gas milestone, our operations team have been working deliberately across multiple work streams. They successfully completed the stimulation campaign on the SS-2 pad in the Betaloo Basin. The program utilized the Liberty Energy stimulation fleet that was imported into the basin in 2023. During the program, we completed 178 stages across 30,000 lateral feet. It was the largest stimulation campaign conducted in the basin. And the Zipper-frac approach allowed us to achieve 20 hours of operations and the Betaloo Basin record 12 stages completed in a day. This gives us and the market early evidence that we can execute completions more efficiently.
The next measure of success is sustaining an improved pace across a full campaign, reducing downtime and bringing down completion cost per well.
We have also entered into a nonbinding memorandum of understanding with Liberty Energy, setting out the intent to extend the hydraulic fracture stimulation and wireline services agreement covering Tamboran's operations in the Betaloo Basin. Liberty intends to begin phasing lower emissions pumping equipment into the Betaloo fleet from 2027. Importantly, the campaign included 10 stages using the locally supplied Betaloo Red Sand across various locations in the SS2-5H well. The pumping and placement of the local sand was an identified risk going into the program. However, given we experienced no impact to pump pressures or fracture initiation during these stages, we are confident on our ability to place local sand in future campaigns. Tracers across the horizontal length have shown that the stages are producing in line with offset wells, but these are still early days, and the true test will be the longer-term flow rates and recoveries. We plan to further test our Betaloo Red Sand during the upcoming stimulation program planned on the SS-1 pad. Success of that local sand is a key step in delivering near-term cost reduction for well completions. It is expected that, that sand could save USD 4 million per well with a 10,000-foot horizontal section compared to the sand imported from overseas. Those long-term flow rates and recoveries from those stages will help us assess how widely we can apply those savings.
In conjunction with the upstream activity, the operations team successfully completed construction of the Sturt Plateau compression facility, on time and approximately USD 9 million below the forecasted budget. This allowed us to meet our commitment to the supply of the Northern Territory gas market during the quarter. The commissioning of the facility remains ongoing as we fine-tune control systems and refine equipment settings. During the commissioning period, we will be receiving 75% of the gas price. This is due to the interruptible nature of the supply. Once commissioning and production testing requirements are complete, we will commence delivery into the take-or-pay contract with the Northern Territory Government.
During the quarter, the operations team also commenced drilling the 3-well campaign on the SS-1 pad with the H&P Flex 3 Rig. Drilling of the first 2 wells has been completed with the third well currently drilling ahead. We continue to incorporate lessons from previous campaigns. This program includes first wells drilled with our improved drill bit design and anti-vibration tools. This resulted in record speeds through the Moroak formation. Modifications to the rig have resulted in reduced mud temps, allowing increased average ROP in the lateral sections. We continue to work with our contract partners to improve efficiencies and reduce downtime, especially within the lateral section, and we believe these are addressable as we ramp up activity.
In the East, drilling of the 2-well appraisal program with Santos on EP 161 has also commenced with the Jibera South 1H and Newcastle South 1H wells in that depocenter. During the quarter, we significantly strengthened our balance sheet. In April, we raised USD 186 million net of fees via an underwritten public offer and an institutional and retail entitlement. The funds from the raise solidify the balance sheet and provide us financial flexibility.
At the end of the quarter, Tamboran had USD 225 million in cash and USD 31 million in undrawn debt for funding of the SPCF, including the USD 15 million that we expect to receive from Daly Waters Energy, the pro forma cash position is USD 240 million. Receipt of that $15 million remains subject to certain conditions precedent. Over the next 2 quarters, we expect that under U.S. GAAP, some revenue and costs related to the Pilot Project will be capitalized to the balance sheet during commissioning, rather than flowing through the income statement. This is to avoid reporting volatility and means that the income statement will not reflect cash movements during the period. We expect to announce first quarterly gas sales and revenue in our 1Q fiscal '27 earnings in November.
The next phase of our development plan is to further delineate our gas resources across both depocenters in the Betaloo Basin. This will be the focus of our '27 and '28 campaigns. We are working with our joint venture partners, Daly Waters Energy and INPEX in the West and Santos in the East to drill and stimulate at least 6 step-out wells over the next 18 months. We are progressing discussions with multiple parties to bring in a strategic partner. These strategic discussions and the upcoming appraisal work, aims to align on resource delineation and commercialization pathways that will support a large-scale development and underpin new pipeline infrastructure. That infrastructure is expected to connect the Betaloo Basin to multiple high-value markets.
To close, we have delivered the First Gas Sales that we committed to 12 months ago and completed the compression facility on time and below the forecasted budget. Our latest drilling and stimulation work is showing where we can improve efficiency, while local sand offers a potential source of completion cost savings. The equity raise has strengthened our balance sheet for the next phase of development. The priority now is to turn those achievements into sustained operating performance. That means completing commissioning and production testing, building towards plateau production and contracted supply and demonstrating that the gains in well delivered can be repeated. Those are the measures, I will use to judge our progress as we advance our development plans and partner discussions.
As we close, I want to thank all Tamboran employees for their commitment, their performance and their support for one another as we continue to grow, evolve and deliver for our customers and shareholders. Thank you.
Operator
[Operator Instructions our first question today is coming from Scott Hanold from RBC Capital Markets.
Preguntas y respuestas
Scott Hanold
Congrats on all the milestones that you guys have achieved and plenty ahead. I want to start maybe focusing on the SS1-6H well. It sounds like it was a pretty successful drill and -- could you give us a sense of what specifically you're changing in your drilling operations to see that success? And what other knobs and dials are you looking forward to doing? And I'm sorry, I'm going to layer on one more thing on this. What kind of cost -- what is that kind of pro forma cost on that now that you've seen some good improvement?
Todd Abbott
Yes, Scott, good to hear from you. Good question. On the 6H and maybe even more broadly kind of on the total drilling program, like the recent changes you'll see there, and I referenced it in the remarks there, the bit design on some of the kind of upper level zones there that we were going through. The vibration damper was actually a pretty big change for us. So that's helped us quite a bit.
I'll also add like one of the things that isn't really a tool change, but the directional plans on those wells and that the way we attack that Moroak Sandstone, which is just a really hard zone, just hard rock to get through. So that's been one of the areas where we saw the biggest opportunities. And in that last well, we got through it with one bit, which was a big win for us. Earlier wells, initial wells on this had many more bits trying to get through that zone. So that's been a key improvement for us. When we look at the kind of opportunities going ahead, we think improving time on our downhole tools is going to help us a lot. We do see opportunities eventually to go to a synthetic oil-based system, which will help our drilling times as well, the ROPs.
And then there's going to be a lot of little things. I mean, I think you've heard me say this before, ultimately, to really get the drilling times and those costs down where we need them to be, we need two things. We need repeatability. So just doing the same thing, same crews, doing it again and again and again. And then the other is scale across the basin. So this is all operators, but having enough critical mass of activity in the basin so that service companies have their center of operations that can be efficient in the way they set up their operations, so that we have readily available tools, readily available people, skill sets, logistics all work better. Everything we've seen in these large shale plays in the U.S. will eventually happen here. But those are the two things that really get it down into those kind of U.S. level cost structures.
Scott Hanold
Good to hear that. My follow-up question is -- and correct me if I'm wrong, it sounds like there's two of the wells that are producing online at this point in time. And could you give us a sense of what you've seen? I know it's still early, but what have you seen on the pressure data on those wells? And are those wells kind of -- have you opened the choke up fully on those? Or are they still choke back here at this point?
Todd Abbott
Yes. I'll say it's been variable on that. The wells look good. They're in line with our expectations. What we're really interested to see on those are the long-term decline rates, and won't know that for a bit. And we haven't produced a well out here for more than 90 days. So specifically, we're working under that 25-terajoule a day nomination limitation. So we're prioritizing 2 wells so that we can develop the production histories and the well performance data to show what the wells can do. But aside from those 2, we've had the other wells cycling on and off kind of as needed, if we need to close the gap to the denomination or as we need to manage getting water off of those wells, kind of helping clean those up. With regard to pressure data, I mean, the pressure data looks good. But again, it's kind of all in line with our expectations. We just need to watch that over time.
Operator
Next question is coming from Leo Mariani from ROTH.
Leo Mariani
I was hoping you maybe talk to what you think CapEx is going to be in the rest of the calendar year. So I guess it would be calendar 3Q and 4Q? Just trying to get a sense of that would be helpful.
Todd Abbott
Yes. And we'll get Chris to kind of go through the specific numbers on it. But I'll tell you, at a high level, we've got 4 wells in the Pilot Area that you'll see 3 this year, 1 next year. We've got the 2 Santos wells over EP 161 with our 25% working interest drill this year, stimulating next year. And then we've got the 4 wells in the BCDA with Daly Waters. It's about a 10% working interest there. So I mean, overall, you can expect our capital to be focused on derisking.
And frankly, the full capital program isn't going to be fully locked-in until we finalize who our partner is and align those, what I would call, collective strategic priorities, kind of where we're going to be in both basins. As you can imagine, each potential partner has a little bit different focus, either one depocenter or the other or for some both. So as those conversations evolve, we'll lock the rest in.
Leo Mariani
Okay. And can you provide a little bit more color on kind of where you are in the process of securing a partner? Do you think that's likely to happen kind of in the next handful of months, which will let you kind of give a better picture of what that kind of '27 calendar year budget would be?
Todd Abbott
Yes, it's certainly moving forward. Look, we continue to see strong outside interest. We're having the right conversations with the right potential partners. I mean, at the end of the day, we're looking for the right capabilities to fit with the strategy and the right time frame with the operation. So I can sympathize with the kind of desire for certainty on the time line, but just please bear with us. It's all in play. And I'm sure everyone appreciates that deals like these take time and need to be carried-out thoughtfully. So we're working through that process. It will -- wherever we land on that, whichever partner we ultimately land with, it will be with a defined work program. And going back to your first question, that will update that capital program.
Operator
Next question is coming from Jeff Grampp from Northland Capital Markets.
Jeffrey Grampp
I was curious with respect to additional in-basin sand testing, I think you said the upcoming fracs will include at least 1 well. I just wanted to clarify, is that something you guys are comfortable doing across the whole wellbore? Will this be another partial test? And then maybe just taking a step back, what do you guys view as kind of the scalability of in-basin supply to the extent you have more confidence there? How meaningful of a portion of the program could that be longer term?
Todd Abbott
Yes. So first, I'll just kind of talk about the early performance. And I mentioned in the remarks, too, we had no problems pumping the sand, which -- that was something we were watching for. We started the fracs, like initiated the fracs well with it. So we're highly confident in our ability to pump it. When we look at the tracers coming back from those stages, they look identical to the other stages and the other wells. So early results are positive. But just like with the production, we won't know the full answer until we get some production history on this and see how all that holds up. So yes, we're optimistic on what it can do.
With regard to these next wells, we won't move to a full Red Sand program until we are confident in it. So we need some of that history. Each well we drill out here is pretty important to help derisk the basin. So we're not going to kind of take outsized risk on any one of them. So we'll do some additional stages on these next completions, but we won't do full wells at this point, Jeff. Going forward, like once we get history on it, once we're comfortable that the Betaloo Red Sand does what we expect and hope it will do, I can see us going to a 100% full program of Red Sand or effectively 100%. There could be some supplements here and there. But I think the end goal is to use in-basin sand in the Betaloo. And from a well cost perspective, it's going to be the obvious right thing to do.
Jeffrey Grampp
Yes. Understood. That makes sense. And for my follow-up, with respect to the potential to expand the SPCF, I think you talked about maybe making an investment decision next year. What are the milestones or key, I guess, check boxes, if you will, to get comfortable making that decision? Is that more on comfortability around your own internal producibility volumes, offtake, financing, all the above? Just any kind of, I guess, kind of milestones to keep an eye out to track that project?
Todd Abbott
Yes. I think all the things you're mentioning are important inputs on it, although I feel pretty good about all the ones you mentioned. The one that we really have to look at, and this is probably the key uncertainty on whether we expand it or not, is making sure that the surrounding infrastructure network will allow us to move the incremental volumes to the incremental markets, right? Just having high confidence that we can get that.
We don't own the pipelines all around us and understanding how the gases are going to flows and how those are going to be upgraded or modified over time will help us make the decision. So we're working through that now, kind of getting a better understanding each day on it. But that's something we just need certainty on before we make that kind of investment. We need confidence that we will be able to...
Operator
Next question is coming from Charles Meade from Johnson Rice.
Charles Meade
Good morning Todd to you, and Eric and Chris and the rest of the Tamboran team. Todd, I want to go back to the -- your decision to flow these -- or really, I guess, prioritize these 2 wells in the initial 25 million cubic feet a day. It seems like getting more production history on more wells is the -- one of the key near-term things that you're looking for. So I'm curious, can you give us an idea when that 25 million cubic feet a day will go to up to the 40 million cubic feet? I mean, I think you said it's contingent on the full commissioning of the SPCF. Can you just give us a time line on when you're going to be able to start to build more of that production history?
Todd Abbott
Yes. Charles, just to make sure I understand your question. You're asking when can we get like -- it's about 25 terajoules now, but when can we get up to the 40 terajoules take-or-pay?
Charles Meade
Yes. And presumably, if you're doing it from 2 wells now, then when you get to 40 terajoules, then you're doing 3 or perhaps even 4 wells. And I guess I didn't do a good job asking the question, but it seems like the data that everyone wants to see are these decline curves. And so when are you going to be able to start building not 2 decline curves, but 3 or 4?
Todd Abbott
Yes. Okay. I understand your question. So yes, on the nominations, right? So the NTG, the Northern Territory Government nominates the gas that they need, right? So right now, because of just where they are seasonally, those needs are not high. So they've limited us to 25 terajoules a day for most days. That will continue kind of in the near term as they move into the wet season, as temperatures rise, you're going to see that load increase, their power generation load increase and thus their gas demand increase.
But just to be clear, I think I said this clearly earlier in the remarks, but not exactly your question, Charles, but for everyone else's benefit, the 25 terajoules a day is a Northern Territory Government limitation, not a well [indiscernible]. So we're meeting that now. We prioritized the 2 wells. Exactly what you're saying, our priority is on generating well history and performance data for these wells long term. So we prioritized the 2 wells. We expect as we move through towards the end of this year, that nomination is going to go up. We're going to get more wells under that.
But to start with, we're prioritizing those 2 wells. And the wells we're prioritizing are both full 10,000-foot lateral and then the well with Betaloo Red sand so that we can get clarity on that data. I think probably by the end of the year, we'll see up with that -- I'm kind of predicting a little bit what they're going to nominate that 40 terajoule a day target. So we'll be able to get more wells in there, Charles, but it's hard to say exactly.
But then later, as we go into next year, we should expect the seasonal restrictions to kind of come back in, and we'll have to pull some of those incremental wells offline. So you won't get the full kind of 12-month history on the other wells, but we are going to prioritize at least 2 wells, so that we can really see the long-term history of what the wells do. Am I answering your question? I feel like I muddled through that.
Charles Meade
No, no, no, you did. That's a great elaboration. And you understood what I was asking even if I didn't make it very clear on my part. But -- and then separately, going in a different direction about the derisking more of the basin. These 2 wells that -- these 2 Santos-operated wells off to the East, can you remind us, I mean, you've shown these logs on Page 12, and it looks thicker over there. You've got multiple landing guards. Can you remind us where -- which of these shale zones you have the laterals targeted-in? And also, can you remind us which of these zones did you test vertically way back in 2021 with that Tanumbirini?
Todd Abbott
Yes. So on the east side, just like the West side, the primary target is the B shale. And if you look on those logs, yes, you can see they vary a little bit, but what you'll see common in both logs is the B shale is the primary target to most people when they will look at it, and both areas have multiple stack pay outside of the B shale, right? So whether you're looking at the A or the C or some of the other things in there. Going back to the history, I'll have to go back and look at the log to see exactly what that well test was. You're predating me a little bit, so I need to go back and check on that. Chris or Eric may hand in on whatever on top of mind...
Eric Dyer
Yes. I mean the -- so there was a vertical frac done by Santos, I want to say, 2019 that hit most of the zones and there was -- one of the lower zones was a bit tight. But look, there's a lot of prospectivity there. The B shale is by far the primary target. But there is some downhole potential and there is some opportunity. But really, that's all off of one vertical frac from 7 years ago. So I think capital is precious, and we've got to be very careful with what we're doing. We're working very closely with Santos to evaluate where we're looking at in that side of the basin. But I do think that, that's one of those things where, in time, there is potential.
Operator
Next question is coming from Paul Diamond from Citi.
Paul Diamond
Circling back to local sand. I guess I know you guys have run the tracer data and talked about 12-month curves being ideal. But I guess can you dig down a little bit there? What are you looking for in that data? I guess what's the hurdle rate on kind of the go or no go for using 100% sand on maybe the 6 wells in the next 18 months or if it's a longer-term narrative?
Todd Abbott
Yes. I mean I would say the real impact of the Red Sand is really in development mode, right, where your capital intensity is higher. We have more wells going in. So we certainly want to have that answer before we get into a development mode. We want to use increasing test as we go forward. What we're specifically looking for in this, is to make sure that the zones where we place that Red Sand hold up on a relative contribution basis over time. Right?
So you can see situations where as the reservoir drawdowns and as those stresses change downhole a bit, the crush pressure for that, that's not a technical term, but can kind of increase over time. We want to make sure that this sand holds up the way the other zones hold up. So that's what we're looking for. We're looking for relative contribution across those different zones and make sure they're comparable. And as long as they are, the cost differences are dramatic, we'll stay with the local sand.
Paul Diamond
Got it. And then switching to Slide 11. You guys show your kind of target of 25 days or less than 25 days. Just trying to get an understanding of, I guess, how -- I guess we're all trying to triangulate CapEx over the long term. But how do you -- how much lower do you think you can get over the course of the next, call it, the 6 delineation wells over the next 18 months? Is 25 days kind of the right number? Or is there a target below that?
Todd Abbott
I think 25 days is a very realistic number for us, and we've actually beat that on other wells, right? We've had a 24-day well. And if you look at our performance in the individual sections of those wells, you add all those up, they're well under the 25 days. On each one, there's kind of been little things here and there that have kept us from doing that, but we're starting to see exactly how we de-bottleneck those processes. So I think you'll see us continuing to improve those. Longer term, I think you could -- especially in the development mode, you should see us setting more ambitious targets than 25 days. But for where we are right now, I think 25 days, is a good target.
Operator
Next question is coming from Anish Kapadia from Hannam.
Anish Kapadia
Just had a question, first of all, in terms of -- I just want to see what needs to happen before the non-binding LOIs that you have for the pipeline get converted into binding GSAs? And when do you realistically expect that conversion to begin? And kind of related to that, what are the remaining commercial regulatory financing milestones for the East Coast pipeline? And what's the kind of current timetable for that binding pipeline development agreement and FID?
Todd Abbott
Yes. So your question is specifically East Coast?
Anish Kapadia
Yes.
Todd Abbott
Okay. Yes. Look, I think APA has been out there pretty actively talking about their work on the East Coast pipeline. They've done a lot of work on both the permitting side and the right-of-way acquisition or [ reason-in ] acquisition to get that and are fairly well progressed. So high confidence that's moving to their credit. They're not really waiting. They're charging ahead on it. From a sequencing standpoint, the way I see that developing is this.
You'll see additional work, like the production data that we're putting on the board from the Pilot Area is probably the biggest piece of information to derisk the subsurface. That's what everybody and kind of everyone on this call and everyone within Tamboran are waiting to see. But that will demonstrate the well decline and the longer-term nature of these wells. Then you've got the other wells that are going in this year.
So the 2 wells over EP 161 are going to be important. The other wells in the West will also correlate. Then over time, and kind of referencing this with our JV process again, there will be other work programs that come out and delineate additional resource. But ultimately, what the industry has to do, and I say that meaning broader than just Tamboran is collectively our work will derisk the resource to merit that infrastructure investment. And that can happen fairly quickly. The resource out here is such that it doesn't take a lot of wells to identify pretty large resource and to merit that large infrastructure investment. So that East Coast pipeline with APA doing their work and with us doing the upstream work, it really derisk the investment.
And we all know that the LNG for this on the East Coast and the new both in the domestic market and in the LNG facilities over there. So GSAs, early conversations are already happening, but there's nothing binding that's going to happen until you have a very clear resource. So I hope that's helpful. That's kind of where the sequence is. It's a little bit hard to say exactly what the timing looks like, but that's the way the sequence will work.
Operator
We reached the end of our question-and-answer session. I'd like to turn the floor back over for any further or closing comments.
Todd Abbott
Listen, guys, we always appreciate the conversations. We're excited about where we're going. We are fully focused on strategically de-risking this play. That's the most important work ahead of us. So the production data is going to go a long ways towards that and then some further delineation work in '27. And I think it's going to be a big year for the basin. So thank you for your engagement, and we'll keep moving on.
Operator
Thank you. That does conclude today's teleconference and webcast. You may disconnect your line at this time, and have a wonderful day. We thank you for your participation.
Este artículo puede incluir contenido generado o traducido por IA que ha sido revisado por personas. Se trata de un contenido que solo tiene propósitos informativos y de referencia, y no constituye un consejo de inversión.
Artículos Recomendados









Comentarios (0)
Haga clic en el botón $, introduzca el símbolo y seleccione si desea vincular una acción, un ETF o otro valor.