CoreWeave’s stock dropped by 16% on Tuesday after CEO Mike Intrator addressed delays linked to a third-party data center developer during the company’s most recent earnings report, according to CNBC.

Mike said the quarter went as planned except for a setback involving what he called “a singular data center provider.”

CNBC host Jim Cramer pushed harder during their live interview, saying some believed the delays were tied to multiple sites, not just one.

Jim named data center facilities in Texas, Oklahoma, and North Carolina, all of which are associated with Core Scientific, the same company CoreWeave tried to acquire earlier this year for $9 billion before shareholders at Core Scientific voted against the deal.

Mike did not confirm that connection. He kept repeating that the issue involved one provider. Shares of Core Scientific also closed 10% lower on Tuesday.

Company sticks to one-provider explanation

During CoreWeave’s quarterly earnings call on Monday, Mark Murphy, an analyst at JPMorgan Securities, asked Mike directly whether Core Scientific was the provider behind the delay.

Mike declined to name the partner, and then at one point in the call, he said only one data center was affected out of 41 data centers in the company’s broader portfolio.

But at another moment, Nitin Agrawal, the company’s CFO, said the issue came from “a single provider, data center provider partner.”

When asked afterward how many sites were impacted, Mike allegedly told CNBC that teams were physically onsite with contractors and Core Scientific workers “every single day” trying to move construction and readiness forward after noticing the slowdown during the third quarter.

He said the company responded by sending its own staff to the facilities to speed up progress and ensure the planned capacity expansion would not fall further behind schedule.

Mike also told analysts that the delays would not affect the company’s backlog or prevent it from realizing the full value of signed contracts.

Revenue rises, guidance falls, deal pipeline remains large

CoreWeave reported $1.36 billion in revenue for its third quarter, a 134% increase from the $583.9 million posted one year earlier.

Even with the strong revenue growth, the company now forecasts 2025 revenue between $5.05 billion and $5.15 billion, lower than the $5.29 billion average estimate from analysts.

The lowered outlook, along with the data center delays, led JPMorgan to downgrade CoreWeave from Overweight to Neutral and reduce its December 2025 price target from $135 to $110, citing rising pressure across infrastructure supply chains.

Despite the downgrade, the analysts said their view of the company’s broader long-term position “remains unchanged,” pointing to increasing demand for high-performance computing capacity across AI development and training workloads.

JPMorgan also said that CoreWeave revenue growth could bounce back in early 2026, assuming the current bottlenecks resolve and planned infrastructure comes online.

CoreWeave has been expanding rapidly as major tech firms compete for GPU-heavy compute.

In September, the company announced a $14.2 billion AI cloud infrastructure agreement with Meta, only days after expanding its existing deal with OpenAI to $22.4 billion. Its backlog nearly doubled quarter-over-quarter to $56 billion, with new customers such as CrowdStrike, Poolside, Rakuten, and Jasper joining the platform.

The delays have become an important test of how fast CoreWeave can turn demand into working infrastructure at scale.

For now, Mike is choosing to hold the line: the company will not publicly blame Core Scientific, even if everyone already knows who the “single provider” is.

Sign up to Bybit and start trading with $30,050 in welcome gifts

ข้อจำกัดความรับผิดชอบ: ข้อมูลที่ให้ไว้บนเว็บไซต์นี้มีไว้เพื่อวัตถุประสงค์ทางการศึกษาและให้ข้อมูลเท่านั้น และไม่ควรถือเป็นคำแนะนำทางการเงินหรือการลงทุน

ความคิดเห็น (0)

คลิกปุ่ม $ ป้อนสัญลักษณ์ และเลือกเพื่อเชื่อมโยงหุ้น, กองทุน ETF หรือสัญลักษณ์หลักทรัพย์อื่น ๆ

0/500
แนวทางการแสดงความคิดเห็น
กำลังโหลด...

บทความแนะนำ

วัน IPO ของ SpaceX เลื่อนเร็วขึ้นเป็นวันที่ 12 มิถุนายน: นักลงทุนควรจับตามองอะไรบ้าง? นักลงทุนในยุโรปและเอเชียจะสามารถซื้อหุ้น SpaceX ได้อย่างไร? ผลกระทบต่อตลาดสหรัฐฯ ในวงกว้างคืออะไร?

TradingKey - เมื่อวันศุกร์ที่ผ่านมา (15 พฤษภาคม) เดอะ วอลล์ สตรีท เจอร์นัล รายงานโดยอ้างอิงแหล่งข่าวที่เกี่ยวข้องว่า SpaceX ของอีลอน มัสก์ มีแผนที่จะเข้าจดทะเบียนในตลาดหลักทรัพย์ Nasdaq อย่างเป็นทางการในวันที่ 12 มิถุนายน ภายใต้ชื่อย่อหลักทรัพย์ “SPCX” โดยมีเป้าหมายการระดมทุนที่คาดการณ์ไว้ที่ 80,000 ล้านดอลลาร์สหรัฐ หรือมากกว่านั้น หากประสบความสำเร็จ การดำเนินการครั้งนี้จะกลายเป็นการเสนอขายหุ้นใหม่แก่ประชาชนทั่วไปเป็นครั้งแรก (IPO) ที่มีมูลค่าสูงที่สุดในประวัติศาสตร์โลก ซึ่งข้อมูลที่เปิดเผยออกมานี้ระบุถึงกำหนดการที่เร็วกว่าแผนการทำ IPO เดิมอย่างมีนัยสำคัญ
ข่าวสารที่สูงสุด
link
ราคาทองคำร่วงลงต่ำกว่า 4,500 ดอลลาร์. โกลด์แมนมีมุมมองเชิงบวก ในขณะที่เจพีมอร์แกนปรับลดราคาเป้าหมายทองคำ; สภาวะตลาดทองคำขาขึ้นจะกลับมาในปี 2026 หรือไม่?
SpaceX แตกหุ้นก่อนทำ IPO, ผลกระทบต่อหุ้นสหรัฐฯ คืออะไร? นักลงทุนรายย่อยควรสังเกตอะไร?
ผลกระทบที่อาจเกิดขึ้นจากการทำ IPO มูลค่า 2 ล้านล้านของ SpaceX ต่อผู้ถือหุ้น Tesla: ข้อเท็จจริง, การคาดการณ์ และสัญญาณการสังเกตที่ตรวจสอบได้สามประการ
รายงานผลประกอบการของ Nvidia กำลังจะมาถึง: นักลงทุนควรให้ความสำคัญกับสิ่งใดมากที่สุด?
หุ้น Micron และ SanDisk ปรับตัวเพิ่มขึ้นท่ามกลางการประท้วงหยุดงานของ Samsung ที่กำลังจะเกิดขึ้น ขณะที่ดัชนีเซมิคอนดักเตอร์ฟิลาเดลเฟียดีดตัวกลับ
KeyAI