CPS Technologies reported record fiscal Q3 2026 revenue of $8.9 million, driven by pricing actions and operational efficiencies that expanded gross margin to 20.9%. Net income rose to $350,000, supported by robust demand for metal matrix composites and hermetic packaging. The company maintains an $18.4 million cash position with zero debt. While inventory increased to prepare for the Attleboro facility relocation, management expects shipments to remain steady, underpinned by a strong order book, defense contracts, and growth in innovative applications like QuickSet Injection Molding, positioning the company favorably for fiscal 2027.

AI-generated summary

Key Takeaways

  • CPS Technologies reported record fiscal Q3 2026 revenue of $8.9 million, up from $8.8 million a year earlier and higher sequentially.
  • Gross margin reached 20.9%, compared with 17.1% in fiscal Q3 2025 and 14.8% in Q2 2026. Management attributed the improvement to pricing and operating efficiencies.
  • Net income rose to approximately $350,000, or $0.02 per share, from approximately $200,000, or $0.01 per share, a year earlier.
  • Cash and marketable securities totaled $18.4 million at quarter-end. CPS had zero debt, while inventory increased to $10.3 million as the company prepared for its facility relocation.
  • Management expects shipments to continue at a similar pace, supported by its order book, stable demand from its largest customer and strong demand for hermetic packaging.
  • CPS expects its new 80,000-square-foot Attleboro facility build-out and moving costs to be within 10% above or below the $9 million net proceeds from its May capital raise.

Key Financial Data

MetricFiscal Q3 2026Fiscal Q3 2025 / ComparisonCommentary
Revenue$8.9 million$8.8 millionQuarterly record; also increased sequentially
Gross profit$1.9 million$1.5 millionImproved economics and operations
Gross margin20.9%17.1%; Q2 2026: 14.8%Highest level in more than three years
SG&A expenses$1.5 million$1.2 millionIncluded $88,000 of noncash lease expense
Operating profit$357,000Slightly below $276,000Higher despite increased SG&A
Net incomeApproximately $350,000Approximately $200,000—
Diluted earnings per share$0.02$0.01—
Cash and marketable securities$18.4 million$13.2 million at the start of 2026Comprised $2.8 million of cash and $15.6 million of securities
Accounts receivable$4.7 million$5.2 million at Dec. 27, 2025—
Inventory$10.3 million$5.6 million at Dec. 27, 2025Increase reflects preparation for the relocation
Payables and accruals$4.6 million$4.3 million at Dec. 27, 2025—

Business and Operating Performance

Demand for metal matrix composite products remains the main driver of CPS Technologies’ capacity expansion. The company secured another set of large orders from its largest customer, a multinational semiconductor manufacturer. Contract demand is consistent with shipments to that customer over the preceding 12 months. CPS components are used in systems supporting high-speed rail, energy and grid infrastructure.

Hermetic packaging also recorded strong demand from aerospace and defense markets and AI-related infrastructure. Management said this demand contributed to fiscal Q3 revenue and is expected to continue.

CPS received its first military contractor order for tungsten alloy components produced with its proprietary QuickSet Injection Molding, or QIM, process. The company expects to fulfill the defense-related contract before year-end. Management views the ability to manufacture larger net-shape components with less post-production machining as a potential source of future revenue growth.

The company’s $1.15 million U.S. Army DEVCOM STTR program, focused on scalable production of a controlled-fragmentation 40-millimeter tungsten warhead, remains on schedule through September 2027.

CPS and Kinetic Protection are also awaiting potential contracts related to congressionally funded HybridTech Armor installations on a small number of Navy destroyer-class vessels. Separately, Navy-funded research continues on reducing the weight of the Amphibious Combat Vehicle using HybridTech Armor and AlMax materials.

Management Outlook

Management expects shipments to continue at a similar pace, citing a strong order book and improved growth outlook for fiscal 2027 and beyond. No specific revenue or margin forecast was provided.

The company’s new Attleboro, Massachusetts facility covers 80,000 square feet, double its current footprint. Build-out work will probably continue into Q4 2027, although CPS is exploring partial occupancy to begin moving earlier in 2027. The current Norton lease expires at the end of February 2028.

CPS estimates that its share of build-out, rigging and moving costs will be within 10% above or below the $9 million net proceeds from its May 2026 registered direct offering. Landlord-funded building improvements are separate from that estimate.

The company will begin paying certain utilities and taxes on June 1, 2027, while rent payments begin on December 1, 2027. CPS expects to convert much of the inventory accumulated for the move back into cash during the relocation, partially offsetting cash expenditures.

Risks and Watch Items

  • Permitting and detailed engineering remain near-term hurdles for the Attleboro build-out. Management said the work is substantial and will take several months.
  • CPS remains space- and capacity-constrained at its current facility, particularly for metal matrix composite production.
  • Inventory increased by $4.7 million from the start of 2026, and management said more than $4.5 million of cash was used this year to build relocation-related inventory.
  • The new lease generated $88,000 of noncash expense in fiscal Q3 under Accounting Standard 842 and will continue to affect reported expenses before cash rent begins.
  • Management identified geopolitical conflicts, economic conditions, market demand and competitive factors as uncertainties that could affect results.

Analyst Q&A Highlights

Management said higher material costs were partly offset through pricing. Gold cost increases are passed through directly to customers, while broader pricing actions and operational efficiencies supported the gross-margin expansion.

CPS has identified capital investments intended to increase production capacity. Purchase timing is being aligned with the facility schedule so equipment can be delivered to the new site. The layout also reserves space for additional capacity if future demand requires it.

On QIM commercialization, management said customer qualification can generally focus on material quality and component dimensions rather than lengthy third-party testing cycles. CPS is discussing larger tungsten alloy components with prospective customers and expects QIM to become an important contributor to revenue growth.

Full Earnings Call Transcript


Complete Earnings Call Transcript

Management Remarks

Operator

Good morning, and welcome to the CPS Technologies Earnings Call. [Operator Instructions]

It is now my pleasure to turn the floor over to your host, Chris Fraser, CFO for CPS. The floor is yours.

Christopher Fraser

Thank you, Sylvie, and good morning, everyone. Today, I'm joined by Brian Mackey, our President and CEO. We look forward to discussing our third quarter results with you. But first, Chris Witty, our Investor Relations advisor, will provide a brief Safe Harbor statement. Chris?

Chris Witty

Thanks, Chris, and good morning, everyone. Before we begin the business portion of today's call, I would like to point out that statements in this conference call that are not strictly historical are forward-looking statements within the meaning of the Private Securities Litigation Reform Act of 1995 and should be considered as subject to the many uncertainties that exist in CPS's operations and environment.

These uncertainties include, but are not limited to, the ongoing conflicts in Ukraine and the Middle East, other geopolitical events, economic conditions, market demands, and competitive factors. Such factors could cause actual results to differ materially from those in any forward-looking statement. Additional information can be found in our filings with the SEC.

Now I'll turn the call over to Brian to offer his perspective on the quarter, after which Chris Fraser will review the financial results in greater detail. Brian?

Brian Mackey

Thank you, Chris, and good morning, everyone, and thanks for joining us today.

I'm pleased to report that third quarter revenue rose to $8.9 million this year, up sequentially as well as year-over-year. This sets a new quarterly record for the company for revenue as we continue to benefit from higher demand and increased production volumes.

At the same time, gross margins rose significantly to 20.9% versus the second quarter's 14.8% and last year's 17.1%. We're very encouraged by the positive momentum we are generating in terms of our growth and overall performance and by the fact that we're on track to move into our new facility during fiscal 2027.

I'll come back and talk more about this in a moment. But first, I'd like to turn the call over to Chris to provide further details about our financial results. Chris?

Christopher Fraser

Thank you, Brian. As we just stated, CPS reported revenue of $8.9 million for the period compared with $8.8 million for the third quarter of fiscal 2025. We anticipate shipments to continue at a similar pace going forward, given our strong book of business and improved growth outlook, positioning us well for fiscal 2027 and beyond.

We reported gross profit of $1.9 million or 20.9% of revenue versus $1.5 million or 17.1% of revenue in fiscal 2025 third quarter, with this year-over-year increase driven by enhanced economics and operational improvements. And our gross margin expanded over 600 basis points from Q2 to the best level in over 3 years.

Selling, general, and administrative, or SG&A, expenses totaled $1.5 million in the third quarter of fiscal 2026, including $88,000 of noncash charges relating to our new lease to make our lease cost consistent over its 12-year term versus SG&A costs of $1.2 million last year. The company posted an operating profit of $357,000 in the current quarter compared with slightly less than $276,000 in 2025. Including other income and taxes, we reported net income of roughly $350,000 or $0.02 per share versus net income of around $200,000 or $0.01 per share in the fiscal 2025 third quarter.

We ended the period with $2.8 million of cash and $15.6 million in marketable securities, or $18.4 million combined. In addition, we also funded a security deposit on the new lease of $0.5 million that is shown as restricted cash in noncurrent assets on our balance sheet.

This compares with $13.2 million at the beginning of 2026, which included $4.4 million in cash and $8.8 million in marketable securities. Trade accounts receivable totaled $4.7 million as of September 26, 2026, versus $5.2 million as of December 27, 2025. Inventories increased to $10.3 million at the end of the third quarter compared with $5.6 million at the start of the year, reflecting our preparation for the move to a new facility.

Turning to the liability side, payables and accruals totaled $4.6 million at the end of the third quarter versus $4.3 million as of December 27, 2025.

Now Brian will provide a more in-depth discussion of the period and outlook. Brian?

Brian Mackey

Thanks, Chris. Now I'd like to provide some additional insight around recent developments and upcoming priorities, starting with our move to a new expanded facility. As previously announced in August, we entered into a lease for 80,000 square feet of space in nearby Attleboro, Massachusetts, which is just a 3-mile drive from our current facility here in Norton.

Detailed planning is well underway with the support of Dacon Corporation, our design-build construction management partner, as well as various engineers and contractors. Upcoming activities include finalizing our floor plan design specifications, including all relevant electrical, plumbing, and mechanical requirements, as well as obtaining appropriate permits from the town of Attleboro.

Based on the amount of work required, which is substantial, it's probable that the build-out will continue into the fourth quarter of 2027. We will be working to accelerate this whenever possible as our construction plans evolve. In addition, we will naturally also be exploring partial occupancy to potentially initiate the move earlier next year.

Ultimately, we expect to relocate our corporate offices, manufacturing operations, and product development activities to Attleboro prior to the lease expiration here in Norton, which does not occur until the end of February of 2028. We wish to move quickly to our new space to benefit from the advantages it provides, but not at the expense of improper planning and design, which is crucial to our long-term success.

The new site, which is double the square footage we occupy today, represents a major milestone in our history and reflects a significant investment that will enable us to capitalize on and support the company's continued growth strategy and expanding customer base while investing in innovative new technologies.

Now that we have increased clarity regarding the work necessary to outfit our new facility and design the intended layout, we're able to generate appropriate cost estimates. As you may recall, back in May of this year, we raised $9.6 million in a registered direct offering. Our current estimate is that the cost to CPS of the build-out, as well as riggers and movers, will be within 10% plus or minus of the amount of capital that we netted from that raise, which was $9 million. This is independent of contributions to be made by our landlord for alterations, improvements, fixtures, and equipment that ultimately enhance the building per the terms of our lease.

Additionally, we continue to review our CapEx needs and lead times to ensure that those expenditures align the additional production capacity with the timing of occupancy of our new facility. It's also worth noting that during our relocation effort, we'll be able to draw from the inventory we've been building throughout the past several quarters.

As Chris mentioned, we have used over $4.5 million of cash this year to build inventories in support of the upcoming move. We expect to convert much of that back to cash during the relocation, which in addition to keeping product flowing to our customers, will partially offset the cash spend of the move.

The initial lease term for the new building started in August, 3 months ago, and runs for 12 years and 10 months. Based on the terms, there is currently no cash impact to CPS. We will begin paying certain charges such as utilities and taxes on June 1 of next year. We will not begin paying rent until December 1, 2027.

However, per Accounting Standard 842, we are now including a monthly lease cost in our noncash expenditures, which Chris alluded to. This began in September and therefore had an $88,000 impact on our Q3 results. Looking to the future, the lease also grants CPS two options to extend the term for 5 years each, generally at fair market prices.

In addition, CPS secured a right of first offer to lease available adjacent space in the building, subject to the terms of the lease, as our current 80,000 square feet represent roughly half of the overall facility size. Overall, we're very pleased with how well the space suits our needs, its close proximity to our current location, the lease terms, and the potential this facility provides to substantially grow the company going forward.

Now I'd like to move on to our current book of business. Typically, around this time of year, we share news of an annual contract with a long-standing multinational semiconductor manufacturer. So I'm pleased to announce that once again, we have secured large orders for our high-performance products from this company, which remains our largest customer.

Demand levels represented by these contracts are consistent with what we've shipped to this client over the preceding 12-month period. Such components from CPS are integrated into systems supporting high-speed rail as well as energy and grid infrastructure. These latest awards underscore our continued confidence in the company's growth outlook, fueled by an ability to deliver next-generation technologies that serve a variety of markets experiencing strong demand.

Our hermetic packaging products are also seeing robust demand, driven by the various markets they support, including aerospace and defense, as well as the build-out of AI-driven infrastructure. This demand was impactful on our Q3 revenue, and we expect this to continue as well. The numerous opportunities we see across the various industries we serve, including defense, energy infrastructure, artificial intelligence, and others, affirm our decision to double our available square footage once we have relocated.

The larger facility will enable us to capitalize on increasing demand with our core metal matrix composite products and hermetic packages, as well as support and advance various growth initiatives, including AlMax materials, HybridTech Armor, QuickSet Injection Molding, and others in ways that we cannot in our current location.

Regarding QuickSet Injection Molding, or QIM, we recently announced our first order from a military contractor for tungsten alloy components manufactured using the company's proprietary process. We're on track to fulfill this defense-related contract before the end of the year.

Our novel manufacturing process enables the production of net shape components with final dimensions and features incorporated directly into the molded product, eliminating the need for extensive post-production machining. QuickSet Injection Molding also enables the efficient production of dramatically larger components, thereby demonstrating greater scalability than traditional metal injection molding.

Although we are unable to share the details of this latest order, it represents a prime example of where our novel manufacturing process is creating new revenue opportunities. Existing injection molding techniques are unable to make these components. As a result, they've typically been manufactured using traditional machining techniques, which are simply inefficient.

We remain optimistic about the future commercialization opportunities that QIM will provide. As a reminder, while we have used QIM for many years in the volume manufacture of certain products of ours, the continued advancement of this technology has been supported through funding from an ongoing Small Business Technology Transfer Award, or STTR, from the U.S. Army DEVCOM, or Army Combat Capabilities Development Command, which is valued at $1.15 million. The work on this program, which is targeting the scalable manufacture of a controlled fragmentation 40-millimeter tungsten warhead, continues to proceed on schedule, and it will run through September of next year.

Lastly, as previously mentioned, congressional funding was approved some time ago to add ballistic shielding using our HybridTech Armor on a small number of Navy destroyer class vessels. We and our partner, Kinetic Protection, remain hopeful that such contracts can be resolved in the coming months. Obviously, we'll keep our investors apprised of new developments going forward.

Along those lines, we also continue our research funded by the Navy, targeting a reduction in the weight of the Amphibious Combat Vehicle, or ACV. Relevant technologies of ours include our HybridTech Armor, which can replace the steel plate mounted to the ACV for ballistic protection, as well as our AlMax material, which offers weight reduction as well as improved corrosion resistance relative to steel components currently used on the ACV.

With increasing demand, new volume orders from our largest customer, an expanded facility in hand, various new product and business development initiatives underway, and ongoing federal review of various proposals for research funding across several agencies, we're very well positioned for continued strong results in the quarters to come.

We believe the company, with a solid balance sheet, including zero debt, an expanding portfolio of innovative applications, and a clear strategy to accelerate growth and improve operating results, is poised for a future that benefits our customers, our employees, and our shareholders better than at any time in our history.

We can now open up the call for questions. Sylvie?

Operator

[Operator Instructions] And your first question will be from Chip Moore at ROTH Capital.

Question-and-Answer Session

Alfred Moore

I wanted to maybe start with the profitability. Gross margin is very, very strong. Nice to see. I guess I thought we might have even seen some higher input costs serving as headwinds or inflationary impacts. Did you see any of that? And could they have been even higher? And what were the main drivers of that profitability?

Christopher Fraser

So some of the impact costs such as gold, and we pass on the exact increment to the customers. We have seen other material costs, but we've done a good job of improving pricing and also operational efficiencies, which have enabled that improvement in gross margin.

Alfred Moore

Got it. That's helpful. And sort of a segue there into 3 miles down the road, I assume that we can see even more efficiencies when we get there. But talk about that move. It sounds like you're planning appropriately. We can see the inventories building and you've got the cash unlock there down the road. But just any longer lead time items that you need to be thinking about? And then on the permitting side, is that sort of the biggest hurdle here near term?

Brian Mackey

Yes. The -- I'll start with the second part of your question, Chip. The permitting side is definitely a hurdle we need to get past. The large amount of effort is the amount of planning required. We have a finalized design for the layout, which we've resolved with Dacon, and now that is being gone over very carefully by the various contracting experts, plumbers, et cetera.

So they're making their detailed plans to satisfy our needs, and that entire package will then be approved for permitting. So a number of steps here. And then, of course, all that work will need to be done, which will take a number of months. So it stretches it out more than we'd like. We're eager to get over there and make use of the better space, but it is going to take a number of months for all those things to play forward.

We do expect some efficiencies over there. You've been through our building here, some others have as well. It's cramped and inefficient. So we're eager to get over there and experience the benefits that, that will offer. It's just going to take us longer than we'd like.

Alfred Moore

Yes. Understood. Yes, do it right. And good to see you thinking ahead to the potential for expanding.

Brian Mackey

So yes, sorry, your first question, we've got a number of CapEx items identified that will improve our capacity. So there's a spend there that we're earmarking, and we're timing those lead times to match our move plan. So as the move has moved a little bit to the right on the calendar, it's given us a little bit of a window to review those things before we place the actual purchase orders, but we have a number of things that we plan to do so that, that equipment is delivered to the new site.

And we also have some things that we've earmarked space for potential future capacity adds that we'll keep in mind as once we occupy that facility, we're laying it out so we have both the near-term add that we know we're going to spend on as well as potential second round of things should the need require it.

Alfred Moore

Perfect. Makes perfect sense. And Brian, your large semiconductor customer gets new annual visibility. I think that $15 million last year. Is that right? And what are you seeing in that market more broadly beyond high-speed rail, but you talked about energy grid and not just with that customer, but potentially with others.

Brian Mackey

Yes. The demand there remains consistent from last year, and we do see that entire market for metal matrix composite products. I mean that's the #1 driver of our need for additional capacity. We're space constrained and capacity constrained here in this facility. And that list of CapEx is -- that I mentioned is definitely a part of our plan for metal matrix composites.

We see that being strong across the board. We have strength in our metal matrix composite expectations as well as hermetic packaging as well as these new things. So it really is true across the board, but the primary one is metal matrix composites.

Alfred Moore

Got it. And maybe if I could sneak one last one in. The commercialization efforts around tungsten alloy, great to see that win. I know you can't speak about that contract specifically, but maybe just the broader opportunity for tungsten alloy components, does that help open things up now that you've got that and what's the potential of your QuickSet process there in that market?

Brian Mackey

Yes. We're very enthusiastic about the opportunities for our QuickSet Injection Molding, starting with tungsten alloy, but there's other materials that we're looking at as well. And part of the nice thing about it is there's not a huge iteration cycle of testing. There's not some multiyear requirement for third-party laboratories or things like that.

Obviously, the customers want to see that the material is properly manufactured, the tungsten alloy is what we say it is, and then that the components are to the right dimensions. But other than those 2 things, it enables really generally a rapid turnaround from interest by the customer to a potential PO to a potential shipment of product by us.

And that's what we're seeing on the order that we're executing now. We expect that to continue. The ability to scale these components up to larger size. We're in discussions now with customers who see that. They see the benefit of it, and we're very interested to see how this plays out, but we think it's going to be a key part of our revenue growth going forward.

Operator

[Operator Instructions] Next question will be from Ron Richards, investor.

Ron Richards

I was going to ask about the possibilities for the tungsten -- the QIM tungsten, you already answered that. So I appreciate the information.

Operator

At this time, it appears we have no other questions registered. I would like to turn the conference over to Brian Mackey.

Brian Mackey

Okay. Great. Thank you, Sylvie, and thanks, everyone, for joining us today and your ongoing interest in CPS. We look forward to speaking with you again at the end of our fourth quarter. If you have any questions in the interim, we hope you reach out to our Investor Relations advisor. Thanks, and good morning.

Operator

Thank you. Ladies and gentlemen, this does indeed conclude your conference call for today. Once again, thank you for attending. And at this time, we do ask that you please disconnect your lines.

This article may include AI-generated content that is human-reviewed, which is for reference and general information purposes only and does not constitute investment advice.

Disclaimer: The information provided on this website is for educational and informational purposes only and should not be considered financial or investment advice.

Comments (0)

Click the $ button, enter the symbol, and select to link a stock, ETF, or other ticker.

0/500
Commenting Guidelines
Loading...

Recommended Articles

tradingkey.logo
Risk Warning: Our Website and Mobile App provides only general information on certain investment products. Finsights does not provide, and the provision of such information must not be construed as Finsights providing, financial advice or recommendation for any investment product.
Investment products are subject to significant investment risks, including the possible loss of the principal amount invested and may not be suitable for everyone. Past performance of investment products is not indicative of their future performance.
Finsights may allow third party advertisers or affiliates to place or deliver advertisements on our Website or Mobile App or any part thereof and may be compensated by them based on your interaction with the advertisements.
© Copyright: FINSIGHTS MEDIA PTE. LTD. All Rights Reserved.